1 general, 2 key interlocks, 3 breaker operation test – GE Industrial Solutions AKD-20 Low Voltage Switchgear Manuel d'utilisation

Page 50: 4 entelliguard trip units

Advertising
background image

AKD-20 Low-voltage Switchgear

Chapter

6.

Testing

and

Inspection

50

©2012 General Electric All Rights Reserved

6-1 General

After the equipment has been installed and all connections made,

it must be tested and inspected before it is put in service.

Although the equipment and devices have been tested at the

factory, a final field test must be made to be sure that the

equipment has been properly installed and that all connections

are correct.

WARNING: The equipment must be completely de-energized

while the tests are in progress.

ADVERTISSEMENT: L’équipement doit être complètement

désamorcé lorsque l’on procède à des tests.

Directions for testing relays, instruments, and meters are given in

the instruction book furnished for each device. The proper

settings of the protective relays and circuit breaker trip units are

normally determined from a complete power system coordination

study performed by the purchaser or their consultant; therefore,

the settings of these devices must be made by the purchaser.

When the equipment is shipped from the factory, the time dial of

all inverse-time induction disc relays (i.e., IFC types) is set to zero to

prevent contact bounce during transportation.

NOTE: The trip setting adjustments of the trip unit for each

circuit breaker may be at any setting when shipped from the

factory and must be correctly set prior to energization of the

equipment.

NOTE: Les ajustements des réglages du disjoncteur peuvent

être en n’importe quelle position lorsque celui-ci est expédié de

l’usine et ils doivent être positionnés correctement avant que

l’équipement ne soit mis sous tension.

General instructions for setting the relays are given in the

applicable Relay or Trip Unit Instruction Book.

The extent of the tests on the equipment as a whole will depend

on the type and function of the equipment. Tests which should be

performed, however, include circuit breaker operation, and

switchgear meggering, phasing, and grounding checks.

High-potential tests to check the integrity of the insulation are not

necessary if the installation instructions are carefully followed. If

local codes demand this test, or the purchaser wishes to make

high-potential tests, the voltage should not exceed 75 percent of

the IEEE factory test voltage.

For the power circuit, the IEEE factory test voltage is two times

switchgear rating plus 1,000 volts. See Table 5-1. Potential and

control power transformers must be disconnected during high-

voltage testing.

Switchgear

Voltage Rating

ANSI

Test Voltage,

ac RMS

Field

Test Voltage,

ac RMS

600V

480V

240V

2200V

1960V

1480V

1650V

1470V

1110V

Table 5-1


6-2 Key Interlocks

After initial installation of the switchgear equipment, all necessary

interlock keys should be inserted into the appropriate locks and all

spare keys should be stored in a location in accordance with the

owner's established procedures.

CAUTION: Refer to the key interlock schematic included in the

summary furnished with the equipment to determine the

sequence of operation and the correct number of operating

keys required. This precaution is necessary since the improper

use of spare keys will defeat the interlocking scheme.

ATTENTION: Référez-vous au schéma des clés de verrouillage

inclus au sommaire fourni avec l’équipement pour déterminer

les séquences d’opération et le nombre correct de clés

d’opération requises. Cette précaution est nécessaire étant

donné qu’un mauvais usage des clés de réserve rendra

inopérant le programme de verrouillage.

6-3 Breaker Operation Test

All compartments housing Entelliguard G circuit breakers have a

TEST position in which the breaker primary contacts are

disconnected while the secondary contacts are still engaged. This

TEST position permits complete testing of the electrical control

circuit without energizing the primary power circuit. When the

breaker is first put into service, its control circuit must be

thoroughly tested while in this position to make sure that all

closing and tripping circuits are complete and functioning

properly.

The TEST position is not suitable for inspection and maintenance

of the breaker and should therefore be used only for testing

breaker operation.

Refer to the appropriate breaker instruction manual for other pre-

operational checks on the breakers. See DEH-41304.

6-4 Entelliguard Trip Units

The calibration of the Entelliguard trip unit should be checked with

the Type GTUTK20 test kit, a portable instrument designed for the

field-testing of Entelliguard trip units. The complete trip system is

comprised of the following components:

1. Solid-state Trip Unit with rating plug


2. Phase Current Sensors


3. Flux Shift Magnetic Trip Device


4. When applicable, a Neutral Sensor for units containing a

Ground Fault Trip element.

Advertising