4-1 General

This chapter contains complete instructions for installing General

Electric AKD-20 Low-voltage Switchgear.

CAUTION: Personnel installing this equipment must be

thoroughly familiar with this instruction manual and all articles of

the National Electrical Code applicable to the installation of this

switchgear. In addition, all drawings, both mechanical installation

and electrical, must be understood and strictly followed to

prevent damage to the switchgear or equipment being protected

by the switchgear.

ATTENTION: La ou les personnes procédant à l’installation de cet

équipement doivent être tout à fait familier avec ce livre

d’instruction ainsi que tous les articles du Code national

d’électricité s’appliquant à l’installation de ce dispositif de

commutation. De plus, tous les dessins se rapportant tant à

l’installation mécanique qu’électrique doivent être compris et

suivis à la lettre afin de prévenir des dommages au dispositif de

commutation ou à l’équipement protégé par celui-ci.

NOTE: Before installation work is started, it is important to

review all of the drawings provided, including the General Electric

equipment arrangement drawings, site installation drawings,

elementary and remote connection drawings, mechanical

connection drawings, and the summary of equipment list.

NOTE: Il est important de reviser tous les dessins fournis, incluant

les dessins de disposition de l’équipement de General Electric, les

dessins d’installation du site, les dessins de raccords

élémentaires et à distance, les dessins de raccords mécaniques

et le sommaire de la liste d’équipement avant que ne débutent

les travaux d’installation.

All expendable hardware for shipping purposes only, is painted

yellow or tagged with yellow adhesive tape and may be discarded

at completion of the installation phase.

Site Location

In general, the location of the switchgear equipment will have been

predetermined during the specification and/or procurement of

equipment phases. Indoor locations within buildings impose certain

requirements which must be met so that the switchgear may

operate efficiently with a minimum of maintenance.

In locating the AKD-20 Switchgear, adequate aisle space must be

provided at the front and rear of the equipment to ensure proper

ventilation of the equipment and to allow service and maintenance

of the equipment with the front and rear doors open. The

recommended aisle space is shown on the floor plan supplied with

the equipment drawings.

The switchgear equipment should be placed in an area where clean,

dry air is free to circulate around and above it. Since air is taken

into the equipment at the bottom of each section and exhausted at

the top, a location with good airflow must be provided for efficient

operation. A minimum of 30 inches of clear space above the

equipment is recommended.



Foundation Requirements

For optimum performance of your General Electric switchgear

equipment, the foundation requirements expressed in this chapter

should be strictly adhered to.

NOTE: The foundation for the outdoor switchgear must provide

proper drainage of ground and/or surface water accumulations

away from the equipment.

NOTE: La fondation du dispositif de commutation situé à

l’intérieur doit être en mesure de drainer correctement les

accumulations d’eau du sol et de surface loin de l’équipement.

The foundation must be strong enough to prevent sagging due to

the weight of the switchgear structure and to withstand the shock

stress caused by the opening of the breakers under fault conditions.

The shock loading is approximately 1-1/2 times the static load.

The foundation must be flat and level in all planes. Refer to Figure 4-

1 for definition of flat and level.

Fig. 4-1. Definition of flat and level

Foundation Preparation

Indoor Equipment

Refer to Fig. 4-2 along with the owner's foundation construction

drawings, and the General Electric supplemental installation

drawings. Although the indoor switchgear equipment can be

mounted directly on a smooth, level floor, it is recommended that

recessed steel channels be installed for supporting the equipment.

Anchor bolts and channels are to be provided by the purchaser.

NOTE: When the equipment is installed on a surface subject to

impact (shock) loads due to operating conditions or

environmental seismic (earthquake) conditions, the anchor bolts

should be fabricated of medium carbon steel (grade 5 load

rating).

NOTE: Lorsque l’équipement est installé sur une surface sujette

à des charges d’impact (choc) causées par les conditions

d’opération ou des séismes environnementaux (tremblements

de terre), les boulons d’ancrage devraient être fabriqués d’acier

à moyenne teneur en carbone (spécification de charge classe

5).

Advertising