GE Industrial Solutions AKD-20 Low Voltage Switchgear Manuel d'utilisation
Page 37

AKD-20 Low Voltage Switchgear
Chapter 4. Equipment Installation
37
©2012 General Electric All Rights Reserved
After completing the installation of the main bus splice bars, the
joint covers may be mounted and secured by a 3/8-16 nylon bolt
and polyester flat washer if the bus insulation option has been
supplied with the equipment.
5. CONNECT THE TRANSFORMER SECONDARY - The connection
of the transformer secondary to the incoming bus bars in the
transition is made using the flexible connection straps
supplied with the transformer. These connections are always
bolted joints.
The recommended torque for tightening the ½-13 bolts fastening
the transformer connection straps to the incoming bus bars is 35-
40 ft-lbs.
6. INTERCONNECT CONTROL WIRING - Interconnection of control
wiring across shipping splits is accomplished by connecting to
terminal blocks located in the cross-section wiring trough on
top of the equipment shown in Fig. 4-16.
If terminal blocks are provided, each wire must be attached to the
correct point on the terminal block, following the circuit
identification number attached to each wire.
Fig. 4-16. Interconnect control wiring is located in the wiring trough
on top of the equipment