Entellisys low voltage switchgear, 3 bus area, 4 cable and busway compartment – GE Industrial Solutions Entellisys Low Voltage Switchgear Manuel d'utilisation

Page 49: 5 overall switchgear

Advertising
background image

Entellisys Low Voltage Switchgear

49

Check and inspect all devices to see that they are functioning

properly. Check that all electrical connections are tight. Check

mounting of the device.

Breaker Compartment Interiors

WARNING: De-energize equipment completely before doing
maintenance work in compartments. This includes de-

energizing any connections to outside primary or secondary
sources, such as transformers, tie lines, etc.

ADVERTISSEMENT: Mettre l’équipement complètement hors
tension avant d’entreprendre tout travail de maintenance sur
tout dispositif, raccordement, barres omnibus ou les

compartiments des câbles d’alimentation. Cela inclut la mise

hors tension des raccordements aux sources primaires et
secondaires tels que les transformateurs et les
interconnexions.

1. Thoroughly clean the interior of the breaker and

instrument compartments. Use a vacuum cleaner and
clean rags only. Do not use steel wool or oxide papers.

Blowing with compressed air is not recommended.

2. Check indicating devices, mechanical and key interlocks.
3. Check primary disconnecting device contacts for signs of

abnormal wear or overheating. Discoloration of the

silvered surfaces is not ordinarily harmful. These contacts
should be cleaned only by wiping with a lint-free cloth.

4. Clean the racking mechanism and lubricate with GE

lubricant D6A15A2.

5. Before replacing the breaker, wipe off the primary

disconnecting device contacts. Apply a thin coat of GE

lubricant D6A15A2 to the stationary studs and to the
primary disconnects on the breaker.

9-3 Bus Area

WARNING: De-energize equipment completely before doing
maintenance work on any devices, connections, bus work,

breaker or feeder cable compartments. This includes de-
energizing any connections to outside primary or secondary
sources, such as transformers, tie lines, etc.

ADVERTISSEMENT: Désamorcer complètement l’équipement
avant d’effectuer du travail de maintenance dans les

compartiments. Cela inclut le désamorçage de toute

connexion aux sources primaires et secondaires, telles que
les transformateurs et les interconnexions.

Inspect and check the bus area as follows:

1. Inspect the buses and connections carefully for evidence

of overheating or weakening of the insulating supports. If
bus insulation is present, remove the molded covers over

the main bus connection to expose joints for inspection.

2. Check all connection bolts in the bus compartment and all

bracing bolts for tightness. See the Torque Table A-1 in

Appendix A.

3. Vacuum and, with a clean rag, wipe the buses and

supports.

4. Visually inspect the insulation on the bars that run from

the breaker studs through the bus structure to the cable
area.

5. After cleaning, megger and record the resistance to

ground and between phases of all insulated bars and all

buses and connections. Disconnect all control circuits

before checking resistance. Do not use over a 1500-volt

megger. Since definite limits cannot be given for satis-
factory insulation resistance values, a record must be kept

of the readings.


Weakening of the insulation from one maintenance period to the

next can be recognized from the recorded readings. The

readings should be taken under similar conditions each time, if
possible, and the record should include the ambient

temperature and humidity.

9-4 Cable and Busway Compartment

Inspect and check the cable and busway compartment as

follows:

1. Inspect all power cable connections for signs of

overheating and tighten all connections. If severe

discoloration or if damage is apparent, remove the
damaged portion of the cable.

CAUTION: Be sure the condition which caused the over-
heating has been corrected before energizing.

ATTENTION: Assurez-vous que la condition ayant causé le
surchauffement a été corrigée avant de mettre sous tension.

2. Check all bolts that hold cable terminals to the

connection bars for tightness.

3. Check the neutral bus and ground bus connection and

mounting bolts for tightness.

4. Check that all secondary control wiring connections are

tight and that all control cabling is intact.

9-5 Overall Switchgear

Make the following checks on the complete switchgear

equipment.

1. Clean and inspect all painted surfaces and retouch where

necessary.

2. Check to see that all anchor bolts and other structural

bolts are tight.

3. Check that all breaker and instrument compartment door

latches operate properly.

4. If the switchgear is equipped with heaters, check to see

that all heaters are energized and operating.

5. For exterior vent openings in equipment furnished with air

filters, the foam filter elements should be removed and

washed in warm soapy water, rinsed, and reassembled at

least annually. Elements should be inspected before re-
assembly and replaced if any signs of deterioration are

evident.

Advertising