Installation & Servicing Instructions Rinnai E-Series

61

13

Maintenance

Maintenance or changes to the boiler may only be carried out by a qualified

technician.

13.1 Periodic examination of venting systems and boiler

The inspection of the boiler and venting system should be done every 2 years and

full maintenance every 4 years or 4000 hours of operation, whichever occurs first..
When doing this the circumstances of the boiler’s location must be taken into account.
From this one can determine whether to deviate from this advice.

Please contact Rinnai for further guidance on the frequency and service

requirements. Contact details can be found on the back page of this manual.

13.2 Inspection

Preparing the boiler for inspection

To carry out the maintenance activities please follow the next procedure:

- switch off the power supply;

- shut off the gas;

- valve off the boiler from the system using the boiler isolation valves in the plumbing

kit.

-

remove the 4 screws A,B,C and D in the quick releases of the casing (figure 29);

- remove the screw E behind the door on the front of the casing (figure 30);
- remove it towards the front.

- clean the casing with a cloth with a simple (non-abrasive) cleaning agent;

NOTICE

i

NOTICE

i

Removing casing figure29

Removing casing figure 30