3-pole branch breaker, A, B, &
C
Ø
location
.
See steps 4a & b.
3-pole disjoncteur de
dérivation, location A, B, &
CØ. Voir Étapes 4a & b.
2-pole branch breaker, A & C
Ø
location
.
See steps 5c & d.
2-pole disjoncteur de
dérivation, location A & CØ.
Voir Étapes 5c & d.
2-pole branch breaker, A &
B
Ø
location
.
See steps 5a & b.
2-pole disjoncteur de
dérivation, location A & BØ.
Voir Étapes 5a & b.
2-pole branch breaker, B &
C
Ø
location
.
See steps 5e & f.
2-pole disjoncteur de
dérivation, location B & CØ.
Voir Étapes 5e & f.
Figure 5. Possible bus strap combinations.
Figure 5. Combinaisons possibles de brides de barre omnibus.
5. Two-pole installations. Use the following procedure for
all two-pole installations (kit AMCB4FGB).
• For installations using phases A and B, continue with
step 5a.
• For installations using phases A and C, go to step 5c.
• For installations using phases B and C, go to step 5e.
5. Installations deux pôles. Utiliser la procédure suivante
pour toutes les installations deux pôles (kit
AMCB4FGB).
• Pour les installations utilisant les phases A et B,
continuer avec l’étape 5a.
• Pour les installations utilisant les phases A et C, aller à
l’étape 5c.
• Pour les installations utilisant les phases B et C, aller à
l’étape 5e.